Intake Process Amendments (Needs Signature)

Content


    Create Amendment

    Select an image to view a larger version.

    Click Create Amendment activity and complete the required fields.

    Upload the draft amendment file or check if the amendment file draft is generated internally. Select +Add to add supporting documentation as needed.

    Select Continue to proceed to Agreement Upload.


    Agreement Upload

    Select the agreement manager and/or principal investigator.

    The title on the SRA should start with Contracting- that way, they know they need to assign this to a Contracting Analyst.

    Type a short name for the agreement. As a guideline, keep it shorter than 50 characters.

    This text appears throughout the system as the agreement name, for example, in My Inbox. This will be automatically generated if left blank and may be changed later.

    Select the appropriate agreement type from the dropdown menu.  Hoover over each type for more information as needed.  Also include a description of the agreement type.

    Indicate only if:

    1. There is a date the Sponsor has specifically required the NDA to be completed by.

    2. There is a scheduled meeting with the Sponsor in which Confidential Information is intended to be exchanged.

    Select Continue to proceed to General Information


    General Information

    The General Information page will populate with questions as shown below.

    1.

    2.

    Provide information for additional external parties or Sponsors that should be an additional party or signatory to the Agreement.

    NOTE
    If it is a multi-party agreement, you will need to enter additional parties here.  Provide information for additional external parties or Sponsors that should be an additional party or signatory to the Agreement.

    3.

    By default, this field displays the organization of Contract Analyst/PI entered on the Agreement Upload page.​ If no value displays, then you must select a value.​

    In case the Contract Analyst/PI is changed in an agreement, the organization value gets updated automatically.​

    In an integrated environment, if an agreement is created from a Funding Proposal or Award, this field populates with the value from the Funding Proposal or Award.​

    NOTE
    If the responsible department doesn’t automatically populate, you will need to designate it here.

    4.

    5.

    A blue circle with a white question mark indicating help text in PERA.This is the Non-Purdue Sponsor Address

    NOTE
    The Contracting Party Business Address needs to be the address of the primary External/Sponsor party named on number one.

    Select Continue to proceed to Sponsored Research Agreement Information.


    Sponsored Research Agreement Information

    Select the Sponsored Research Agreement type from the dropdown menu.

    Select Continue to proceed to Completion Instructions.


    Completion Instructions

    When you click Finish on the Completion Instructions page, you have not yet finished all the steps to send the agreement for review. You have the option to continue editing the agreement.

    Before the Agreement Office can review it, you must submit it for review from the workspace. You will find the submit options after you click Finish.


    Submit

    To submit, click on the Submit activity on the Dashboard. 

    Double-check your information.

    Once finished, click OK. Contracting will review the Agreements Unassigned list to assign to an analyst.


    Assign Owner

    1. Click on the Unassigned activity in the Dashboard.

    2. Open the Agreement.

    3. Assign Owner activity.  Whoever is assigned also needs to be assigned as the Primary Contact. Also, Manage Access to update to the person assigned as the Owner (analyst assigned).

    4. Once finished, click OK.

    Launch team will get the AMA from the Award Administrative Contact. Email sent to AMA by system that they’ve been assigned as owner.


    8. Email Agreement

    Once the AMA is fully executed, click on Email Agreement in the Agreements Module.

    Select the recipient of the email as the Setup Manager, Suzanne Payne.   Add attachments to the email, including a pdf of the email.  You will need to create the pdf first and then attach it.  Once finished, click OK.

    You can locate the History Tab to ensure that the email was sent.

    The AMA will attach documents from the email received to the award (attachments).

    The Setup Manager will then receive the email and will click on the link in that email. The Setup Manager will then complete the Assign Specialist task to assign to the Setup Administrator for processing.


    Content Updated: